Bus and train services will be operating on the inner Armadale Line from Sunday, 8 June with special event services and regular services commence Monday, 9 June.
Long Park and some parking and amenities are not yet available as we complete construction in the station precincts. Work will progress in the station precincts over the coming weeks, with amenities becoming available as they are completed.
We recognise the impact that the Armadale Line shutdown has had on the community and the return to services has been prioritised. Stations will be impacted with some station entry points not yet open, parking, bike storage and other amenities are still being worked on.
Your patience and understanding are appreciated as we work to complete the station precincts.
For detailed information regarding what is available at your station, please visit Stations & Maps. For station specific information click on the links for Carlisle Station, Oats Street Station, Queens Park Station, Cannington Station and Beckenham Station.
Accessibility
- We are working with accessibility groups to ensure they are aware of access arrangements for the stations.
- ACROD parking is not yet available at Oats Street and Cannington stations. We recommend utilising parking available at Carlisle, Queens Park and Beckenham stations while we work to complete the car parks at Oats Street and Cannington.
Bike users
- We are working to have bike parking facilities complete and open for use as soon as possible. If you are planning on riding a bike to the station, we recommend using Carlisle or Queens Park Station. Secure bike parking is available at these stations. We encourage passengers to keep an eye on the Transperth Website as there may be changes to disruptions.
Motorists
- Parking and drop off bays are currently unavailable at Cannington Station. We recommend utilising parking available at Carlisle, Queens Park and Beckenham stations while we work to complete the car park.
- Drop off bays are unavailable at Oats Street Station for the next few weeks. We recommend utilising parking available at Carlisle, Queens Park and Beckenham stations while we work to complete the car park.
Pedestrians
- Some station access points are located in areas still under construction, please follow signage on site to access the station.
- We encourage passengers to keep an eye on the Transperth Website as there may be changes to disruptions.
Stay up to date
The METRONET and Transperth websites will be updated as this work is progressed over the coming weeks.