Works

Works

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Out-of-hours works

The following activities may take place out-of-hours as required:

  • relocating existing utility services (water, gas, electricity, and telecommunications)
  • concrete pouring 
  • delivery and installation of retaining walls, abutment walls, columns, headstocks and concrete beams for the elevated rail
  • Concrete beam delivery and unloading for the Eleventh Road bridge and Larsen Road pedestrian bridge
  • road works
  • mobilising equipment, rigs, and cranes to site.
  • beam installation
  • refuelling

For more information, see the out-of-hours works page here.


Service relocation works (until late 2024) 

service relocation works are ongoing at:

  • Alexander Road, Byford
  • Larsen Road, Byford
  • Evans Way, Byford
  • George Street, Byford 

Armadale Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Elevated rail extended out-of-hours works

Ongoing out-of-hours work throughout the Armadale area between Gladstone Road and Prout Road, see map below for reference. Dates and locations are subject to change.


Overnight beam deliveries (until October 2024)

Out-of-hours delivery and installation of 125 oversized concrete beams for the elevated rail bridge will be ongoing until October 2024. Oversized loads must be moved outside of peak traffic times to comply with Main Roads requirements for transporting.

Upcoming beam delivery and installation:

  • Haul route 3: Armadale Road, Aragon Court
    • 22 July 2024 
    • 24 July 2024
    • 25 - 27 July 2024
    • 29 July 2024
  • Haul route 2: Hobbs Drive, Church Avenue
    • 22 July 2024
    • 23 July 2024
    • 24 July 2024
    • 26 July 2024
    • 29 - 31 July 2024

*Dates subject to minor change due to weather and other factors

Beams will be delivered via the haul routes shown on the map below:


Armadale Road (until mid-2025)

  • Ongoing works to widen Armadale Road between Church Avenue and Abbey Road. 
  • The speed limit on Armadale Road is reduced to 40km/h
  • Armadale Road will be reduced to a single lane in each direction until mid-2025
  • Streich Avenue-Armadale Road intersection will be closed until early-2025 with no access to turns or crossing at that intersection
  • Alternative access to Armadale Road has been created by connecting the cul-de-sac on Glastonbury Road to Streich Avenue

Armadale Road Fact Sheet


Orchard Avenue night works and closure (4 August 2024)

Orchard Ave will be closed between Armadale Road and Neerigen Street overnight on the 4 August to enable the safe installation of;

  • Traffic Control Barriers
  • Changing the traffic arrangement on Orchard Avenue 

Traffic management will be in place for the duration of the works.


Elevated rail bridge retaining walls (until late-September 2024)

Works to install retaining walls to support the elevated rail bridge are ongoing in the rail corridor between: 

  • Frys Lane pedestrian crossing and Gladstone Road, Armadale until late-August 2024 
  • Coombe Avenue and Prout Road, Armadale until late-September 2024

Works include:

  • excavating to prepare the area 
  • installing precast concrete retaining walls using a crane 
  • backfilling and compacting general fill between the retaining walls

There will be noise, dust and vibration from equipment, heavy vehicles, machinery and work activity, and a significant increase in heavy vehicle traffic.

 

Byford Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


 Alexander Road, Byford (11 March to late July 2024)

  • There will be no pedestrian access along Alexander Road until late August 2024. Pedestrians will be required to use the footpath on Araucaria Boulevard and Halfpenny Avenue.  


Larsen Road pedestrian bridge (until November 2024)

  • Works involve the installation of bridge footings, deflection walls and bridge structure.

Overnight beam deliveries (mid-August 2024)

Out-of-hours delivery and unloading of oversized concrete beams for the pedestrian bridge will be ongoing until mid-August 2024. Oversized loads must be moved outside of peak traffic times to comply with Main Roads requirements for transporting.

Beam delivery route will travel northbound on South Western Highway, westbound on Larsen Road and then turn left into the rail corridor to unload the beams .

Upcoming beam delivery dates:

  • Tuesday, 23rd July 2024
  • Thursday, 25th July 2024
  • Friday, 26th July 2024
  • Wednesday, 31st July 2024
  • Saturday, 3rd August 2024

Evans Way and George Street:

  • Earthworks have commenced to complete the section of George Street between Larsen Road and Evans Way
  • Evans Way and George Street intersection will be closed from 15 June to 30 September 2024 to enable drainage installation and to rebuild the intersection.
  • there is no pedestrian access along George Street between Evans Way and Larsen Road
  • pedestrians can use the shared path on South Western Highway.


Byford Station (until August 2024 )

  • Vegetation removal and pruning will continue within the rail corridor adjacent to Evans Way, George Street and Abernethy Road until August
  • at times, workers will be present on the verge of George Street and traffic management will be in place, reducing the speed limit to 40km/h.

Eleventh Road Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Eleventh Road (until mid 2025)

Eleventh Road is now closed for 10 months between Gull Street / Lambert Lane and Bruns Drive east to enable the construction of the bridge.

The temporary closure is required to ensure works are undertaken as quickly and as safely as possible, minimising inconvenience to road users and nearby residents.

Road users will be required to use Church Avenue or Thomas Road to cross the rail line during the closure. Pedestrians and cyclists will not be permitted to access the closed section of Eleventh Road. Cyclists will need to follow the detour routes. 

Access to Fletcher Park will be maintained via Stone Street, Moore Street and Mitchell Street.

Concrete pours and bridge panel installation for the bridge structure are ongoing.


Overnight beam deliveries (until 31July 2024)

Out-of-hours delivery and unloading of oversized concrete beams for the road bridge will be ongoing until 31 July 2024. oversized loads must be moved outside of peak traffic times to comply with Main Roads requirements for transporting.

Beam delivery route will travel northbound on south western highway, westbound on eleventh road and then turn left into the rail corridor to unload the beams 

upcoming beam delivery dates:

  • Wednesday, 24 July 2024

Bruns Drive west

The intersection of Eleventh Road and Bruns Drive west has been temporarily closed to rebuild the intersection of Bruns Drive and Eleventh Road to support local access during the Eleventh Road closure.

Road users will be required to follow the detour in place as per the map below:


Wungong Brook Rail bridge works 

  • ongoing concrete pours
  • earthworks to backfill bridge abutments
  • retaining wall installation is ongoing.

 

Byron Road level crossing

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


As part of the METRONET Byford Rail Extension Project, the Byron Road level crossing is permanently closed.  

To maximise safety for road users, Main Roads WA, on behalf of METRONET, has been undertaking intersection upgrades, including road widening on South Western Highway at Eleventh Road, Stone Street and Dickens Road.

Traffic signal installations at Eleventh Road and Stone Street have been unavoidably delayed, we appreciate your patience while we work through how the temporary intersection treatments will operate.


Traffic signal installation – Stone Street and Eleventh Road

Traffic movements at the intersections of Eleventh Road and Stone Street are being managed until permanent traffic signals are installed.

The intersections at Eleventh Road and Stone Street will operate under temporary traffic management as unsignalised T-intersections supported by temporary traffic signals that will operate, as needed, during peak periods. The temporary management is supported by interim line markings, signs, and additional lighting to delineate the lane alignments at each intersection to support traffic movements.

Under the temporary conditions, Main Roads will be monitoring the road environment to assess traffic flows and will operate the temporary traffic signals as needed i.e. due to excessive queuing.

Byron Level Crossing Fact Sheet

Out-of-hours works

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Elevated rail extended out-of-hours works

Ongoing out-of-hours work throughout the Armadale area between Gladstone Road and Prout Road, see map below for reference. Dates and locations are subject to change.


Armadale elevated rail overnight beam deliveries (until October 2024)

Out-of-hours delivery and installation of 125 oversized concrete beams for the elevated rail bridge will be ongoing until October 2024. Oversized loads must be moved outside of peak traffic times to comply with Main Roads requirements for transporting.

Upcoming beam delivery and installation:

  • Haul route 3: Armadale Road, Aragon Court
    • 22 July 2024 
    • 24 July 2024
    • 25 - 27 July 2024
    • 29 July 2024
  • Haul route 2: Hobbs Drive, Church Avenue
    • 22 July 2024
    • 23 July 2024
    • 24 July 2024
    • 26 July 2024
    • 29 - 31 July 2024

 

*Dates subject to minor change due to weather and other factors

Beams will be delivered via the haul routes shown on the map below:


Armadale Road closures (3 – 15  July 2024)  

Armadale Road will be closed between Abbey Road and Orchard Avenue on the following dates to enable safe installation of concrete planks and crane movements for the elevated rail bridge.

  • 1am on Saturday 13 July until 4am on Monday 15 July

Traffic management will be in place for the duration of the works.


Orchard Avenue night works and closure (29 July 2024)

Orchard Ave will be closed between Armadale Road and Neerigen Street overnight on the 29th July to enable the safe installation of;

  • Traffic Control Barriers
  • Changing the traffic arrangement on Orchard Avenue 

Traffic management will be in place for the duration of the works.


Forrest Road weekend closure (20 – 21 July 2024)

Forrest Road will be closed between Abbey Road & Neerigen Street from 2am Saturday 20 July until 9pm Sunday 21 July for the installation of concrete beams to support the elevated rail bridge.

24/7 works will be required with no vehicle or pedestrian access within the closure. Detours and traffic management will be in place for the duration of the closure to assist path and road users. 

Traffic detour map 

Pedestrian detour map


Eleventh Road Overnight beam deliveries (until 31 July 2024)

Out-of-hours delivery and unloading of oversized concrete beams for the road bridge will be ongoing until 31 July 2024. 

Beam delivery route will travel northbound on South Western Highway, westbound on Eleventh Road and then turn left into the rail corridor to unload the beams 

Upcoming beam delivery dates:

  • Thursday, 18 July 2024
  • Wednesday, 24 July 2024   

Larsen Road Overnight beam deliveries (mid August 31 July 2024)

Out-of-hours delivery and unloading of oversized concrete beams for the pedestrian bridge will be ongoing until 31 July 2024. 

Beam delivery route will travel northbound on South Western Highway, westbound on Larsen Road and then turn left into the rail corridor to unload the beams.

Upcoming beam delivery dates:

  • Tuesday, 16 July 2024
  • Saturday, 27 July 2024
  • Friday, 2 August 2024

Works Alerts

Stay up to date with project works around your area via SMS and email alerts.

Works Alerts

Stay up to date with project works around your area via SMS and email alerts.

Back To Top