Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.
Elevated rail extended out-of-hours works
Ongoing out-of-hours work throughout the Armadale area between Gladstone Road and Prout Road, see map below for reference. Dates and locations are subject to change.
Temporary disruption at the Armadale Road and Abbey Road intersection
The left turn lane from Armadale Road westbound, into Abbey Road will be temporarily closed from Monday 16 September until Monday 30 September to complete road widening and pavement works.
Vehicles less than 12.5m will be able to turn left onto Abbey Road at the traffic lights. To avoid congestion please consider turning left at Orchard or Church avenues instead.
Vehicles longer than 12.5m will need to use the detour at Gribble Avenue. Please see the map below for alternative routes.
Armadale Road (until mid-2025)
- Ongoing works to widen Armadale Road between Church Avenue and Abbey Road.
- The speed limit on Armadale Road is reduced to 40km/h
- Armadale Road will be reduced to a single lane in each direction until mid-2025
- Streich Avenue-Armadale Road intersection will be closed until early-2025 with no access to turns or crossing at that intersection
- Alternative access to Armadale Road has been created by connecting the cul-de-sac on Glastonbury Road to Streich Avenue
Armadale Road Fact Sheet
Orchard Avenue night works and closure (15-16 September 2024)
Orchard Ave will be closed between Armadale Road and Neerigen Street overnight from 7pm Sunday 15 September until 5am Monday 16 September to enable the safe installation of;
- Traffic Control Barriers
- Changing the traffic arrangement on Orchard Avenue
Traffic management will be in place for the duration of the works.
Forrest Road weekend closure (21 – 22 September 2024)
Forrest Road will be closed between Green Avenue & Commerce Avenue from 4am Saturday 21 September until 10pm Sunday 22 September for the installation of concrete planks to support the elevated rail bridge.
24/7 works will be required with no vehicle or pedestrian access within the closure. Detours and traffic management will be in place for the duration of the closure to assist path and road users.
Traffic detour map:
Pedestrian detour map:
Structural steel installation at Armadale Station (until early-October)
Out-of-hours works will be required to install structural steel for the new Armadale Station buildings. Works will be ongoing from 7pm until 7am, until early-October.
Overhead Line Equipment Works (until Early September)
Foundation Piling works for the overhead line mast installation will be ongoing until early September 2024.
Works will be undertaken within the rail corridor between Barge Court and Eleventh Road, Wungong, from 7am to 7pm, Monday to Saturday. Works include:
- installing two underground piles for the overhead line equipment mast every 52m (approximately 8 per day)
- two types of drills will be used to conduct the piling works;
- an auger drill (a large spiral shaped drill) to install steel reinforcement cages and filling the piles with concrete
- a hammer drill to install concrete piles.
Works will progress rapidly along the rail corridor, with noise and vibration impacts to individual properties expected to last one day (subject to change).
Elevated rail bridge retaining walls (until late-September 2024)
Works to install retaining walls to support the elevated rail bridge are ongoing in the rail corridor between:
- Frys Lane pedestrian crossing and Gladstone Road, Armadale until late-August 2024
- Coombe Avenue and Prout Road, Armadale until late-September 2024
Works include:
- excavating to prepare the area
- installing precast concrete retaining walls using a crane
- backfilling and compacting general fill between the retaining walls
There will be noise, dust and vibration from equipment, heavy vehicles, machinery and work activity, and a significant increase in heavy vehicle traffic.
Changes to Site Compound (16 September – Late January 2025)
We are expanding site facilities to support the building works for Armadale Station. These changes will occur from 16 September 2024 to late January 2025 at the existing site compound on Wungong Road, Brookdale, from 7am to 7pm, Monday to Saturday.