Works

Nicholson Road Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. 


Site works (ongoing)

Delivery of materials to site, earth works, drainage and relocation of underground services.
Trucks and water carts will access the site via Tulloch Way and Canna Drive, Canning Vale.
Some carpentry and steel work will take place at the Station building site, during night shifts, Monday to Friday. There will be early starts, Monday to Friday from 5:45am. 

Station entryway construction

On Saturday 22 and Sunday 23 March, traffic management will be in place on Tulloch Way, near the Nicholson Road Station site to support works on the station’s entryway.
Access to driveways and properties will be maintained.

Nicholson Road southbound temporary road and path closures

To allow for the safe delivery and installation of large pre-cast concrete underpass arches and wall segments, there are planned closures of the Nicholson Road southbound carriageway between Bannister Road/ Wilfred Road and the Yale Road/ Garden Street roundabout at the following times:

  • from 7pm Friday 28 March until 4am Monday 31 March
  • from 7pm Friday 11 April until 4am Monday 14 April

Signed detours will be in place via Bannister Road/ Ranford Road and Spencer Road/ Yale Road.

Construction work will continue 24/7 during these periods on Nicholson Road and the underpass at Nicholson Road, with site access via Nyandi Court, Wilfred Road and the Nicholson Road Station site.

 
 

Ranford Road Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.   


Irrigation works

Until the end of March, there will be night works and traffic management in place at Ranford Road to install irrigation at Ranford Road Station. Works will occur between 7pm and 7am and there will be some lane closures in place. 

Thornlie Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts.

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Station work

Construction is underway to make Thornlie Station a through station, including removal of some redundant sections of the existing station. 


Rail Works - Out-of-Hours Jandakot, Canning Vale, Thornlie and Kenwick 

The newly installed rail network will be adjusted, in preparation for passenger trains to use this new rail.

This will involve:

  • installing and adjusting OLE using specialised equipment
  • installing and testing signalling and communications equipment.

During March, between 6pm and 6am, nightly, rail work will take place in the Glen Iris rail tunnel in Jandakot, the rail bridge over the Canning River in Kenwick and the rail tunnel between Kenwick and Beckenham.


Temporary lane closure on O’Dell Street

Until the end of April 2025, the eastbound lane of O’Dell St will be temporarily closed to allow safe construction of a retaining wall and new noise wall in the area.
Access to properties will be maintained and detours will be in place.


Temporary closure of Spring Road Reserve

The Spring Road Reserve is temporarily closed to support construction until the end of the Thornlie-Cockburn Link project. Please, use Banksia Circle Reserve instead. The detour route is shown in the map below.


Monopole installation

As part of the Radio Systems Replacement project, a monopole will be installed within the Thornlie Station car park. 

Works are ongoing until the end of March. The installation may have some noise impacts on nearby residents. 


Rail access, relocation, O'Dell Street, Thornlie

The existing rail access point on O’Dell Street will be relocated further along O’Dell Street, approximately 80 meters south-east.

From mid-March, works to relocate the access point will include locating underground services, clearing vegetation and concreting.


Reinstatement of O'Dell Street and Spring Road Reserve, Thornlie 

From mid-March, there will be works to reinstate O’Dell Street and Spring Road Reserve which includes reinstating the kerb and path, concreting and revegetation. 

 

Rail Corridor

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am. 

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts.

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Testing and commissioning

From mid-March until mid-May, testing and commissioning will be taking place, alongside driver familiarisation. Trains will be operating along the line, in preparation for entry into revenue service.  


Building rail infrastructure

Works within the Mandurah Line rail corridor (along Kwinana Freeway) between Roe Highway and Russell Road/Gibbs Road, and at the Glen Iris Rail Tunnel:

  • delivery and unloading of materials
  • track construction
  • installing overhead line equipment
  • installing signalling, power and communications equipment and cables
  • rail testing and adjusting.

Works within the freight rail corridor and Thornlie Line passenger rail corridor between the Glen Iris Rail Tunnel, Jandakot and Beckenham Street / Dulwich Street, Beckenham include:

  • installing and adjusting track, ballast, sleepers and overhead line equipment
  • earth works and concreting
  • installing underground services and drainage
  • building retaining and noise walls
  • installing fencing
  • delivery and unloading of materials

Upcoming night works in the Mandurah Line rail corridor

Between Glen Iris rail tunnel (south of Roe Highway) and Aubin Grove Station, as well as in and around the Glen Iris rail tunnel and Cockburn Central Station, out-of-hours works are currently planned on the following dates:

  • 20 & 21 March
  • 24, 26, 27 and 30 March 
  • 2 and 3 April
  • 9 & 10 April

Traffic management will be required on the Kwinana Freeway in support of some of these works. See Main Roads WA signage and website for details.

Existing site compounds, material stockpiles and site access / egress points will be used to support these out-of-hours works, which may result in additional noise during the night. 


Rail works - out-of-hours Jandakot, Thornlie, Kenwick & Beckenham

The newly installed rail network will be adjusted, in preparation for passenger trains to use this new rail.

This will involve:

  • installing and adjusting OLE using specialised equipment
  • installing and testing signalling and communications equipment

During March, between 6pm and 6am, nightly, rail work will take place in the Glen Iris rail tunnel in Jandakot, the rail bridge over the Canning River in Kenwick and the rail tunnel between Kenwick and Beckenham.


Monopole installation

As part of the Radio Systems Replacement project, a monopole will be installed within the Thornlie Station car park. 

Works are ongoing until the end of March. The installation may have some noise impacts on nearby residents. 


Roadworks at Training Place in Jandakot

From Monday to Saturday, from 7am to 7pm, there will be works at the intersection of Hope Road and Training Place, resulting in an increase in noise levels. These works will involve roadworks, asphalting, line marking and sign installation.


Signalling works – out-of-hours

There will be signalling works along the rail corridor, works will move from Jandakot to Thornlie Station to complete cable hauling, install signalling equipment and electrical terminations. This work will take place from Sunday night to Saturday morning from 6pm to 6am. 


Building foundations and piers, Jandakot 

There will be work activities in the Glen Iris Drive cul-de-sac alleyway to build foundations and piers for the acoustic gate. This will involve the use of a concrete pump and may require some temporary traffic management in this area of Glen Iris Drive.


Wall construction and painting, Canning Vale and Jandakot

There will be an increase in noise during works to build and paint walls along the south side of the rail corridor between Marginata Parkway and Nicholson Court, Canning Vale, and next to Glen Iris Drive, Turtle Point Cove, Lakes Way and Clements Place Jandakot, and on the north side of the corridor near some properties on Wittenberg Drive and Uppsala Place, Canning Vale.


Rail access construction, Canning Vale

There will be works to build the rail access track and connection points, in the McLean Road verge on the rail corridor side, where McLean Road is parallel to the railway, as well as in the rail corridor between Dowarn Green and Tulloch Way. This will involve excavating, placing and compacting materials, concreting and accessing the site via the local road.

A new rail access point will be built at the end of the Fairfield Gardens cul-de-sac, nearby Fairfield Park and connecting to the Mesa Place cul-de-sac. This will involve installing temporary and permanent fencing and barriers, delivering and moving construction equipment and materials, vegetation clearing where required, excavating, placing and compacting materials. Works take place between 7am and 7pm daily.

A temporary path closure will be in place until early April to support some rail access construction.

The closure and detour details are below.


Dewatering, Canning Vale and Thornlie

Possible increase in noise from 24/7 use of a pump and generator within the work sites near:

  • Canning River, west of Rimmer Lane, Kenwick
  • Southdown Place, Thornlie
  • O’Dell Street, Thornlie
  • Fairfield Gardens, Canning Vale
  • Nicholson Road Station, Canning Vale

Level crossing permanent closure, Thornlie

The Elliot Place / Cameron Street pedestrian level crossing is permanently closed. Please use the signed detour routes shown in the map below.

The project includes a new footbridge to replace this crossing, providing safer access for pedestrians and cyclists.


Rail access construction and use, Thornlie 

Work will take place to upgrade the existing rail access point between Nyandi Court and the rail corridor. This will then be used to support construction activities in the rail corridor. At times traffic management will be needed on the local road.


Drain and road access construction, Thornlie

Until end-September 2025, there will be works to remove redundant underground services, build a new drain and access road on the north side of the rail corridor near Southdown Place and Corriedale Reserve, Thornlie. This may result in more noise in the area when these works are happening.


Site facility changes and traffic management, Thornlie

The site laydown and parking area on Cameron Street is being extended along the verge and into the road, to support drain and footbridge construction. This involves traffic management on Cameron Street.

The northbound lane of Cameron Street, next to the cul-de-sac, will be temporarily closed until May 2025. Access to properties will be maintained.


Wall construction and painting, Thornlie

There will be an increase in noise during works to build and paint retaining and noise walls on the south side of the rail corridor between Nyandi Court and Kidman Court, and O’Dell Street between Spring Road and Canning River Bridge, and on the north of the rail corridor behind properties on Southdown Place, adjacent to Corriedale Reserve, Thornlie.


Drainage installation and retaining wall work, Thornlie

From end-March to mid-2025, there will be works to upgrade the local drainage network at the Southdown Place cul-de-sac in conjunction with City of Gosnells works to replace a retaining wall and reinstate the local road.

There will be a temporary partial road and path closure with traffic management in place. Access to driveways and properties will be maintained at all times.


Rail access, relocation, O'Dell Street, Thornlie

The existing rail access point on O’Dell Street will be relocated further along O’Dell Street, approximately 80 meters south-east.

From mid-March, works to relocate the access point will include locating underground services, clearing vegetation and concreting.


Reinstatement of O'Dell Street and Spring Road Reserve, Thornlie 

From mid-March, there will be works to reinstate O’Dell Street and Spring Road Reserve which includes reinstating the kerb and path, concreting and revegetation.  


Thornlie Station – Out-of-hours works

Service installation will be carried out during night shift, Monday to Friday from 7pm to 7am, in the Thornlie Station area and to the west of the station carpark, adjacent to Kidman Court, Thornlie.


Canning River path closure, Thornlie

Canning River path under the rail bridges, near O’Dell Street Reserve and Southdown Place/Corridale Place, Thornlie, is closed until April-2025 with a signed detour in place


Rail access construction, Beckenham

There will be upgrades to the existing rail access point and use of the temporary site facility, in the verge of Albany Highway, south-east of the intersection with Sevenoaks Street, Beckenham.


Rail tunnel upgrade, Kenwick

There will be regular night shifts to support upgrade work inside the tunnel and in the rail corridor near the Thornlie Line rail tunnel, between Kenwick and Beckenham.


Noise wall construction, Kenwick

There will be an increase in noise during works to remove the existing wall, and build and paint a noise wall along Burham Road, in Kenwick. Works will be ongoing until the end of April, Monday to Saturday from 7am to 7pm. 


Site facilities and access points

Out-of-hours works to support and access site at:

  • the bushland south of Berrigan Drive and west of the Kwinana Freeway, via Verna Court, Cockburn
  • Mellor Place, Bibra Lake
  • west of Kwinana Freeway, via Nettle Way, South Lake
  • the corner of Karel Avenue and Berrigan Drive, Jandakot
  • Karel Avenue, west of Orion Road, Jandakot
  • Fairfield Gardens, Canning Vale 
  • McLean Road, Canning Vale 
  • Nicholson Road Station site, Canning Vale
  • Nyandi Court, Thornlie
  • Tom Bateman Reserve on Wilfred Road, and Cameron Street, Thornlie
  • Spencer Road, Thornlie
  • Cameron Street, Thornlie
  • Elliot Place, Thornlie
  • O’Dell Street Reserve and Spring Road Reserve, Thornlie
  • East of Canning River with access via Rimmer Lane, Kenwick
  • Packer Park, Burham Road, Kenwick
  • Albany Highway, near Sydenham Street, Beckenham.

Cockburn Central Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. 


Rail infrastructure (ongoing)

Works within the Mandurah Line rail corridor (along Kwinana Freeway) between Roe Highway and Russell Road/Gibbs Road, and at the Glen Iris Rail Tunnel: 

  • delivery and unloading of materials
  • track construction 
  • installing overhead line equipment
  • installing signalling, power and communications equipment and cables
  • rail testing and adjusting.

Perth Stadium Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. 


Rail Changes

When the Thornlie-Cockburn Link Project is operational, residents in the southern suburbs and along the Mandurah Line will be able to catch a train to Optus Stadium and the Crown Resort at Burswood, without needing to transfer through the Perth CBD. To facilitate this, adjustments need to be made to the rail around Perth Stadium Station.

Service interruptions and traffic management are required to support these essential works, which will impact community members. Please visit the Transperth and Main Roads websites for assistance in journey planning. 


Rail Construction, Burswood

Rail adjustments and installation to accommodate the future Thornlie Cockburn Link services, including installing drainage, and underground services, as well as installing and adjusting track, overhead line equipment, signalling and communications equipment. This will likely result in more vehicular traffic and increase noise levels in the area.

Out-of-hours works are planned, from 7pm to 7am, including public holidays, are planned on the following dates:

  • 6 to 11 April

Traffic management will be required, including on the Victoria Park bridge over rail and Graham Farmer Freeway. See Variable Message Boards and the Main Roads WA website for details.


Storage area, Summers Street/East Parade, East Perth (in use until April 2025)

A laydown area is being used to support project rail upgrade works at and around Perth Stadium Station. This will involve moving and storing construction equipment and materials, resulting in more noise in the area.

Out-of-hours works will be required intermittently, from 7pm to 7am, including:

  • Until 15 March
  • 6 to 11 April 

For further information on train and bus services, head to the Transperth website.

Back To Top