Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.
All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts.
For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.
Building rail infrastructure
Works within the Mandurah Line rail corridor (along Kwinana Freeway) between Roe Highway and Russell Road/Gibbs Road, and at the Glen Iris Rail Tunnel:
- delivery and unloading of materials
- track construction
- installing overhead line equipment
- installing signalling, power and communications equipment and cables
- rail testing and adjusting.
Works within the freight rail corridor and Thornlie Line passenger rail corridor between the Glen Iris Rail Tunnel, Jandakot and Beckenham Street / Dulwich Street, Beckenham include:
- installing and adjusting track, ballast, sleepers and overhead line equipment
- earth works and concreting
- installing underground services and drainage
- building retaining and noise walls
- installing fencing
- delivery and unloading of materials
Upcoming night works in the Mandurah Line rail corridor
Between Glen Iris rail tunnel (south of Roe Highway) and Aubin Grove Station, as well as in and around the Glen Iris rail tunnel and Cockburn Central Station.
Night shifts are currently planned on the following dates:
- 3 to 5 December
- 8 to 12 December
- 15 to 19 December
- 27 to 30 December
- 5 to 9 January
- 12 to 17 January
Traffic management will be required on the Kwinana Freeway in support of some of these works. See Main Roads WA signage and website for details.
The team will also use existing site compounds, material stockpiles and site access / egress points to support these night works.
Track adjustment - Out-of-hours
Until 20 December the newly laid track will be adjusted, in preparation for passenger trains to use this new rail. This will include tamping and regulating, using large machinery to shift the ballast rock and adjust the level of the rail to meet stringent quality specifications. This rail adjustment work will take place from 7am until 5pm, from Monday to Sunday. Work will generally move progressively from Kenwick towards Jandakot.
Night shifts are currently planned on the following dates:
- 1 to 20 December from 6pm to 5am
Roadworks at Training Place in Jandakot
From Monday to Saturday from 7am to 7pm, there will be works at the intersection of Hope Road and Training Place. We are upgrading the intersection, installing, and relocating services and drainage. These works will involve roadworks, cutting and asphalting.
Night shifts are currently planned on the following dates:
- 1 to 6 December from 6pm to 5am
Building foundations and installing transformer units, Jandakot
Until early-December there will be work activities in the Glen Iris Drive cul-de-sac alleyway to build foundations and install transformer units. This will involve the use of a concrete pump and may require some temporary traffic management in this area of Glen Iris Drive.
Wall construction, Canning Vale and Jandakot
There will be an increase in noise during works to build walls along the south side of the freight rail corridor between Marginata Parkway and Nicholson Court, Canning Vale, and next to Glen Iris Drive, Turtle Point Cove, Lakes Way and Clements Place Jandakot.
Rail access construction, Canning Vale
There will be works to build the rail access track and connection points, in the McLean Road verge on the rail corridor side, where McLean Road is parallel to the railway, as well as in the rail corridor between Dowarn Green and Tulloch Way. This will involve excavating, placing and compacting materials, concreting and accessing the site via the local road.
Temporary rail access construction, Canning Vale
There will be works to build a temporary rail access track and connection points, in between the rail corridor and the path that is parallel to the rail corridor, nearby Fairfield Gardens. This will involve potholing and surveying to identify underground services, adjusting temporary fencing and barriers, clearing vegetation, delivering, and moving construction equipment and materials and excavating, placing and compacting materials including fill, limestone and asphalt.
Works will be ongoing until early 2025, Monday to Saturday 7am to 7pm.
Drainage installation, Canning Vale
Until 19 December, from 7pm to 7am, Monday to Friday, drainage installation will be carried out on the southern side of the rail corridor in Canning Vale, between Nicholson Road and Ranford Road. The crews will work in a 600m long section at a time, across the period of around one week, progressing from west to east.
Sewer relocation, Canning Vale
Sewer upgrade work is taking place in the rail corridor, near Fairfield Gardens. This will involve tunnelling and the use of cranes. There will be some occasional Sunday work. Dewatering will take place 24/7. The footpath in this area is temporarily closed.
Dewatering, Canning Vale and Thornlie
Possible increase in noise from 24/7 use of a pump and generator within the work sites near:
- Canning River, west of Rimmer Lane, Kenwick
- Southdown Place, Thornlie
- O’Dell Street, Thornlie
- Fairfield Gardens, Canning Vale
- Nicholson Road Station, Canning Vale
Level crossing permanent closure, Thornlie
The Elliot Place / Cameron Street pedestrian level crossing is permanently closed. Please use the signed detour routes shown in the map below.
The project includes a new footbridge to replace this crossing, providing safer access for pedestrians and cyclists.
Rail access construction and use, Thornlie
Work will take place to upgrade the existing rail access point between Nyandi Court and the rail corridor. This will then be used to support construction activities in the rail corridor. At times traffic management will be needed on the local road.
Site facility changes and traffic management, Thornlie
The site laydown and parking area on Cameron Street is being extended along the verge and into the road, to support drain and footbridge construction. This involves traffic management on Cameron Street.
The northbound lane of Cameron Street, next to the cul-de-sac, will be temporarily closed until March 2025. Access to properties will be maintained.
Retaining wall / noise wall construction, Thornlie
There will be an increase in noise during works to build retaining and noise walls on the south side of the freight rail corridor between Nyandi Court and Kidman Court, and O’Dell Street between Spring Road and Canning River Bridge, Thornlie.
Out-of-hours works
There will be panels installation in the rail corridor near some houses along Nyandi Court and Carakine Grove between 8 and 20 December. Works will occur from 7pm to 7am
Thornlie Station – Out-of-hours works
Service installation will be carried out during night shift, Monday to Friday from 7pm to 7am, in the Thornlie Station area and to the west of the station carpark, adjacent to Kidman Court, Thornlie.
Spencer Road bridge – Out-of-hours works
On 9 December from 6pm to 5am the team will be installing electrification protection screens on the Spencer Road bridge over the rail line in Thornlie.
Canning River path closure, Thornlie
Canning River path under the rail bridges, near O’Dell Street Reserve and Southdown Place/Corridale Place, Thornlie, is closed until mid-2025 with a signed detour in place
Rail access construction, Beckenham
There will be upgrades to the existing rail access point and use of the temporary site facility, in the verge of Albany Highway, south-east of the intersection with Sevenoaks Street, Beckenham.
Beckenham traction power substation upgrade
Until February 2025, works are required to upgrade infrastructure along the network in order to support the passenger railway. The existing traction power substation in the verge of Railway Parade, East Cannington, north of the Crawford Street intersection, is part of the infrastructure that has been identified for upgrade. A generator will operate 24 hours a day. Traffic management will also be regularly used in this area.
Until December, night and weekend works will take place at this site, this will involve the use of lighting towers.
Building a new signalling equipment room in Kenwick
A new Signalling Equipment Room (SER) will be built to connect train communication services between the Thornlie-Cockburn Link and the Armadale Line. Monday to Saturday, 7am to 7pm.
Communications and Signalling
Works related to Victoria Park please refer to Victoria Park-Canning Level Crossing Removal
Upgrading rail corridor fencing, communications and signalling between Beckenham and Kenwick stations, with a shared path detour between Ladywell Street and Wanaping Road, until Friday 13 December.
Rail tunnel upgrade, Kenwick
There will be regular night shifts to support upgrade work inside the tunnel and in the rail corridor near the Thornlie Line rail tunnel, between Kenwick and Beckenham.
From 11 to 16 December from 6pm to 5am the team will be installing electrification protection screens on the Kenwick Link bridge over the railway.
Site facilities and access points
Out-of-hours works to support and access site at:
- the bushland south of Berrigan Drive and west of the Kwinana Freeway, via Verna Court, Cockburn
- Mellor Place, Bibra Lake
- west of Kwinana Freeway, via Nettle Way, South Lake
- the corner of Karel Avenue and Berrigan Drive, Jandakot
- Karel Avenue, west of Orion Road, Jandakot
- Fairfield Gardens, Canning Vale
- McLean Road, Canning Vale
- Nicholson Road Station site, Canning Vale
- Nyandi Court, Thornlie
- Tom Bateman Reserve on Wilfred Road, and Cameron Street, Thornlie
- Spencer Road, Thornlie
- Cameron Street, Thornlie
- Elliot Place, Thornlie
- O’Dell Street Reserve and Spring Road Reserve, Thornlie
- East of Canning River with access via Rimmer Lane, Kenwick
- Packer Park, Burham Road, Kenwick
- Albany Highway, near Sydenham Street, Beckenham.