Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. For all out-of-hours works, please contact the site supervisor directly on 0437 845 471.
Lane closures (ongoing)
Until November, Chesham Rise and Charlbury Drive northbound lanes will be closed to build retaining and noise walls. Traffic will be one-way southbound, with left-turns only permitted onto the thoroughfare.
Earth works (ongoing)
Until 5 February, Water Corporation are installing sewer services on Sundays from 7am–3pm at Santorini Promenade Bridge between Chico Link and Missingham Avenue.
Until February, preparation for retaining walls to be built within the rail corridor between Bluewater Drive and Alkimos Drive bridge, south of Bainbridge Avenue.
Out-of-hours works from 6am until late-March to compact earth from Romeo Road to Bainbridge Avenue, and install services at Romeo Road Bridge.
Until June, clearing vegetation, installing drainage and basins, and building road connections south of Bainbridge Avenue and Bowline Avenue, Alkimos.
Until June, machinery will move and compact earth between Butler Station and Howden Parade.
Bridge works (ongoing)
Building the Romeo Road and Howden Parade road-over-rail bridges in the rail corridor between Darbyshire Parade and Alkimos Station site. Subject to weather conditions, there will be out-of-hours concrete pours to build the bridge foundations.
Until March, night works from Monday to Sunday to build Romeo Road Bridge.
Until February, utility services will be installed around Santorini Promenade Bridge. Works include excavation, drainage installation, verge clearance, pavement construction, kerbing, asphalting, and barrier installation to realign the road.
Until February, trucks will access site via Bluewater Drive and Maroon Avenue to pour concrete and install steel reinforcement to build the Alkimos Drive bridge, south of Bainbridge Avenue.
Until mid-February, road realignment along Santorini Promenade will include asphalting and sealing new roads, in addition to the installation of new kerb and barriers.
Intermittent lane closures (until mid-2023)
Cranes and piling rigs are being delivered to the rail corridor to build retaining walls. Lane closures will be in place on Santorini Promenade, Chico Link and Charlbury Drive.
Heavy vehicle crossings (until mid-2023)
Traffic management will be in place intermittently Monday to Friday, to enable passage of heavy vehicles from the access gates across Bainbridge Avenue between Maroon Avenue and Buchannan Avenue.
Retaining walls (ongoing)
Building retaining walls to support the eastern side of the rail corridor between Butler Station and Howden Parade.
Until February, installing piles and precast panels to build retaining and noise walls on the eastern side of the rail corridor from Santorini Promenade to Howden Parade. Trucks will transport excess earth from rail corridor via Darbyshire Parade.
Night works from 7pm–7am until late-April to excavate and transport earth between Butler Station and Howden Parade.
Until late-2023, a site compound will be installed on Santorini Promenade, Alkimos and on Doncaster Grange, Butler to facilitate building retaining and noise walls.
Until late-2023, noise wall works along Duerden Street, Alkimos, including vegetation clearance, relocation of fencing, installation of piling pads, compaction, operation of piling rigs and widening of an access gate.