Works

Nicholson Road Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. 


Site works (ongoing)

Delivery of materials to site, earth works, drainage and relocation of underground services.
Trucks and water carts will access the site via Tulloch Way and Canna Drive, Canning Vale.
Some carpentry and steel work will take place at the Station building site, during night shifts, Monday to Friday. There will be early starts, Monday to Friday from 5:45am. 

Road works (ongoing)

There will be an increase in noise, speed restrictions and lane closures during works on Nicholson Road between Hughes Street/Gateway Boulevard and Canna Drive, Canning Vale.

An altered road alignment and temporary traffic configuration will be in place on Nicholson Road between Hughes Street/Gateway Boulevard and Passenger Place/Canna Drive, Canning Vale, with detours in place.


Businesses on Nicholson Road remain open

Attention all shoppers! Nicholson Road shops are OPEN for business!

Despite the road closures, find your way to Nicholson Road and continue supporting local businesses.

Temporary driveway closures are in effect for some businesses along Nicholson Road between Hughes Street and Passenger Place. Additionally, road closures are in place on Panama Street and Vostan Road until late-October.


Night road works

From 4 to 22 November between 6pm and 7am, night works are required on the following roads:

  • Tulloch Way from Panama Street to Nicholson Road Station
  • Panama Street from Tulloch Way to Nicholson Road, and
  • Nicholson Road from Tulloch Way to Passenger Place.

The works will include resurfacing the road and installing line markings and traffic loops.

There will be restricted access to some driveways along these roads during this time. Traffic management will be in place.

 

 

 

Ranford Road Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.   


Ranford Road (ongoing)

Works to build the new Ranford Road Bridge are underway and traffic management, including altered signals and traffic configuration is in place in the area.

Thornlie Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts.

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Station work

Construction is underway to make Thornlie Station a through station, including removal of some redundant sections of the existing station.


Track adjustment

Until end-November, the newly laid track will be adjusted, in preparation for passenger trains to use this new rail. This will include tamping and regulating, using large machinery to shift the ballast rock and adjust the level of the rail to meet stringent quality specifications. This rail adjustment work will take place from 7am until 5pm, from Monday to Sunday. Work will generally move progressively from Thornlie towards Jandakot.


Temporary lane closure on O’Dell Street

Until end of April 2025, the eastbound lane of O’Dell St will be temporarily closed to allow safe construction of a retaining wall and new noise wall in the area.
Access to properties will be maintained and detours will be in place.


Temporary closure of Spring Road Reserve

The Spring Road Reserve is temporarily closed to support construction until the end of the Thornlie-Cockburn Link project. Please, use Banksia Circle Reserve instead. The detour route is shown in the map below.


Retaining walls/noise wall construction (ongoing)

A temporary closure of the eastbound lane will be in place on O’Dell Street to support the safe construction of a retaining wall and a noise wall.

Access to properties will be maintained with traffic management and detours in place. Please drive safely and follow the detour signs.

There will be an increase in noise during retaining wall construction works at Thornlie Station car park.

Impacts to the car park are in place, see signage onsite for parking bay availability.


Installing drainage and underground services

There will be an increase in noise and traffic management in place on O’Dell Street, Thornlie to support the installation of drainage and underground services in this area and the nearby rail corridor.


Thornlie Station – Out of hours works

Service installation will carry out on night shift, Monday to Friday from 7pm to 7am, in the Thornlie Station area and to the west of the station carpark, adjacent Kidman Court, Thornlie.

Rail Corridor

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am. 

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts.

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Building rail infrastructure

Works within the Mandurah Line rail corridor (along Kwinana Freeway) between Roe Highway and Russell Road/Gibbs Road, and at the Glen Iris Rail Tunnel:

  • delivery and unloading of materials
  • track construction
  • installing overhead line equipment
  • installing signalling, power and communications equipment and cables
  • rail testing and adjusting.

Works within the freight rail corridor and Thornlie Line passenger rail corridor between the Glen Iris Rail Tunnel, Jandakot and Beckenham Street / Dulwich Street, Beckenham include:

  • removing and installing track, ballast, sleepers and overhead line equipment
  • earth works and concreting
  • removing and installing underground services and drainage
  • building retaining and noise walls
  • installing fencing
  • building the rail embankment and foundation
  • delivery and unloading of materials

Installing electrified passenger rail assets 

Unlike the existing freight line, passenger trains run on electricity and specific infrastructure is needed to ensure the safe and effective running of services. This is being installed across the corridor and includes track and signalling equipment, as well as:

  • overhead line equipment - wires, masts and gantries to support the electrified rail system. This equipment transfers the 25,000 volts of power needed to power electric trains
  • location cabinets, signalling equipment rooms and trackside equipment rooms - that house signalling, power and communications equipment
  • radio masts - support rail communications

This equipment and technology support the network by providing:

  • high-capacity signalling
  • train control, including safety systems
  • security and CCTV
  • passenger information systems
  • radio and telecommunications
  • remote monitoring

Storage area, Summers Street/East Parade, East Perth (in use until April 2025)

The team are establishing and using a laydown area to support project rail upgrade works at and around Perth Stadium Station. This will site investigations, installing fencing as well as moving and storing construction equipment and materials.


Upcoming night works in the Mandurah Line rail corridor

Between Glen Iris rail tunnel (south of Roe Highway) and Aubin Grove Station, as well as in and around the Glen Iris rail tunnel and Cockburn Central Station.

Night shifts are currently planned on the following dates:

  • 24 to 28 November
  • 1 to 5 December
  • 9 to 13 December
  • 16 to 20 December
  • 27 to 30 December
  • 6, 8 & 9 January
  • 13 to 19 January

Traffic management will be required on the Kwinana Freeway in support of some of these works. See Main Roads WA signage and website for details.

The team will also use existing site compounds, material stockpiles and site access / egress points to support these night works.


Rail tunnel upgrade

There will be regular night shifts to support upgrade work inside the tunnel and in the rail corridor near the Thornlie Line rail tunnel, between Kenwick and Beckenham.


Building a new Signalling Equipment Room in Kenwick

A new Signalling Equipment Room (SER) will be built to connect train communication services between the Thornlie-Cockburn Link and the Armadale Line. Monday to Saturday, 7am to 7pm. 


Communications and Signalling

Works related to Victoria Park please refer to Victoria Park-Canning Level Crossing Removal

Upgrading rail corridor fencing, communications and signalling between Beckenham and Kenwick stations, with a shared path detour between Ladywell Street and Wanaping Road, until Friday 13 December.


Rail access construction, Beckenham

There will be upgrades to the existing rail access point and use of the temporary site facility, in the verge of Albany Highway, south-east of the intersection with Sevenoaks Street, Beckenham.


Beckenham Traction Power Substation Upgrade

Until February 2025, works are required to upgrade infrastructure along the network in order to support the passenger railway. The existing traction power substation in the verge of Railway Parade, East Cannington, north of the Crawford Street intersection, is part of the infrastructure that has been identified for upgrade. A generator will operate 24 hours a day. Traffic management will also be regularly used in this area.

Unitl December, night and weekend works will take place at this site, this will involve the use of lighting towers.


Canning River path closure, Thornlie

Canning River path under the rail bridges, near O’Dell Street Reserve and Southdown Place/Corridale Place, Thornlie, is closed until the end of 2024 with a signed detour in place


Cameron and Elliot Footbridge – Out of Hours works

From 26 November to 29 November between 7pm and 7am there will be heavy vehicles along Cameron St and Wilfred Rd.  The team will be lifting and placing precast ramps using large cranes in the Cameron and Elliot bridge.


Retaining wall / noise wall construction, Thornlie

There will be an increase in noise during works to build retaining and noise walls on the south side of the freight rail corridor between Nyandi Court and Kidman Court, and O’Dell Street between Spring Road and Canning River Bridge, Thornlie. 

Out-of-hours works 

There will be panels installation from the rail corridor in some houses along Nyandi Court and Carakine Grove between 10 November and 6 December. Works will occur from 7pm to 7 am.


Thornlie Station – Out-of-hours works

Service installation will be carried out during night shift, Monday to Friday from 7pm to 7am, in the Thornlie Station area and to the west of the station carpark, adjacent to Kidman Court, Thornlie.


Track Adjustment

Until end-November, the newly laid track will be adjusted, in preparation for passenger trains to use this new rail. This will include tamping and regulating, using large machinery to shift the ballast rock and adjust the level of the rail to meet stringent quality specifications. This rail adjustment work will take place from 7am until 5pm, from Monday to Sunday. Work will generally move progressively from Thornlie towards Jandakot.


Site facility changes and traffic management, Thornlie

The site laydown and parking area on Cameron Street is being extended along the verge and into the road, to support drain and footbridge construction. This involves traffic management on Cameron Street.

The northbound lane of Cameron Street, next to the cul-de-sac, will be temporarily closed until March 2025. Access to properties will be maintained.


Level crossing permanent closure

The Elliot Place / Cameron Street pedestrian level crossing is permanently closed. Please use the signed detour routes shown in the map below.

The project includes a new footbridge to replace this crossing, providing safer access for pedestrians and cyclists.


Rail access construction and use, Thornlie 

Work will take place to upgrade the existing rail access point between Nyandi Court and the rail corridor. This will then be used to support construction activities in the rail corridor. At times traffic management will be needed on the local road.


Dewatering, Canning Vale and Thornlie

Possible increase in noise from 24/7 use of a pump and generator within the work sites near:

  • Canning River, west of Rimmer Lane, Kenwick
  • Southdown Place, Thornlie
  • Thornlie Station
  • O’Dell Street, Thornlie
  • Greenway Avenue, Thornlie
  • Tarradee Circuit, Cameron Street and Elliot Place, Thornlie
  • Kanani Drive Reserve on McLean Road, Canning Vale
  • Sorbonne Crescent, Canning Vale
  • Fairfield Gardens, Canning Vale

Sewer Relocation, Canning Vale

Sewer upgrade work is taking place in the rail corridor, near Fairfield Gardens. This will involve tunnelling and the use of cranes. There will be some occasional Sunday work. Dewatering will take place 24/7. The footpath in this area is temporarily closed. 


Drainage installation

Between 13 November and 19 December, from 7pm to 7am, Monday to Friday, drainage installation will be carried out on the southern side of the rail corridor in Canning Vale, between Nicholson Road and Ranford Road. The crews will work in a 600m long section at a time, across the period of around one week, progressing from west to east.


Noise wall panel installation

Between 13 and 22 November, from 7pm to 7am, noise wall panels will be placed along the southern rail corridor boundary near Parkland Trail / Pinewood Walk and near Meadowview Mews / Steppe Court and Woodhouse Park in Canning Vale.


Wall construction, Canning Vale and Jandakot

There will be an increase in noise during works to build walls along the south side of the freight rail corridor between Marginata Parkway and Nicholson Court, Canning Vale, and next to Glen Iris Drive, Turtle Point Cove, Lakes Way and Clements Place Jandakot.


Rail access construction, Canning Vale

There will be works to build the rail access track and connection points, in the McLean Road verge on the rail corridor side, where McLean Road is parallel to the railway, as well as in the rail corridor between Dowarn Green and Tulloch Way. This will involve excavating, placing and compacting materials, concreting and accessing the site via the local road.

Temporary Rail access construction, Canning Vale 

There will be works to build a temporary rail access track and connection points, in between the rail corridor and the path that is parallel to the rail corridor, nearby Fairfield Gardens. This will involve potholing and surveying to identify underground services, adjusting temporary fencing and barriers, clearing vegetation, delivering, and moving construction equipment and materials and excavating, placing and compacting materials including fill, limestone and asphalt.

Works will be ongoing until early 2025, Monday to Saturday 7am to 7pm.


Roadworks at Training Place in Jandakot

From Monday to Saturday from 7am to 7pm, there will be works at the intersection of Hope Road and Training Place. We are upgrading the intersection, installing, and relocating services and drainage. These works will involve roadworks, cutting and asphalting.

Night shifts are currently planned on the following dates:

  • From 18 to 22 November from 6pm to 5am
  • From 25 to 29 November from 6pm to 5am
  • 4 and 5 December from 6pm to 5am

Building foundations and installing transformer units, Jandakot 

Until early-December there will be work activities in the Glen Iris Drive cul-de-sac alleyway to build foundations and install transformer units. This will involve the use of a concrete pump and may require some temporary traffic management in this area of Glen Iris Drive.


Site facilities and access points

Out-of-hours works to support and access site at:

  • the bushland south of Berrigan Drive and west of the Kwinana Freeway, via Verna Court, Cockburn
  • Mellor Place, Bibra Lake
  • west of Kwinana Freeway, via Nettle Way, South Lake
  • the corner of Karel Avenue and Berrigan Drive, Jandakot
  • Karel Avenue, west of Orion Road, Jandakot
  • Fairfield Gardens, Canning Vale 
  • McLean Road, Canning Vale 
  • Nicholson Road Station site, Canning Vale
  • Nyandi Court, Thornlie
  • Tom Bateman Reserve on Wilfred Road, and Cameron Street, Thornlie
  • Spencer Road, Thornlie
  • Cameron Street, Thornlie
  • Elliot Place, Thornlie
  • O’Dell Street Reserve and Spring Road Reserve,Thornlie
  • East of Canning River with access via Rimmer Lane, Kenwick
  • Packer Park, Burham Road, Kenwick
  • Albany Highway, near Sydenham Street, Beckenham.

Cockburn Central Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. 


Rail infrastructure (ongoing)

Works within the Mandurah Line rail corridor (along Kwinana Freeway) between Roe Highway and Russell Road/Gibbs Road, and at the Glen Iris Rail Tunnel: 

  • delivery and unloading of materials
  • track construction 
  • installing overhead line equipment
  • installing signalling, power and communications equipment and cables
  • rail testing and adjusting.

Perth Stadium Station Area

Standard work hours are Monday to Saturday, 7am–7pm, and any out-of-hours works are indicated below. Some activities across the project work site will start from 6am.

All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. 

For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666. 


Rail Changes

When the Thornlie-Cockburn Link Project is operational, southern suburbs’ and Mandurah Line residents will be able to catch a train to Optus Stadium and the Crown Resort at Burswood, without needing to transfer through the Perth CBD. To facilitate this, adjustments need to be made to the rail around Stadium Station.


Rail Construction, Burswood

Rail adjustments and installation to accommodate the future Thornlie Cockburn Link Services, including installing drainage, electrification screening and underground services, as well as constructing rail foundations, involving earthworks and compaction.

Night works are planned, from 7pm to 7am, including public holidays, are planned on the following dates:

  • 25 to 28 November
  • 1 to 3 December
  • 4, 5, & 8 December
  • 9 to 15 December
  • 16 to 19 December
  • 10 to 16 January

Traffic management will be required, including on the Victoria Park bridge over rail. See Main Roads WA signage and website for details.

For further information on train and bus services, head to the Transperth website.

Back To Top