Works

Works

Standard work hours are Monday to Saturday, 7am-7pm, and any out-of-hours works are indicated below. All works will follow approved noise and traffic management plans, and every effort will be made to minimise impacts. For questions about project works, please email info@metronet.wa.gov.au or call 9326 3666.


Night works (7–11 August)

Installing screens on the overpass bridge, building platform canopies and formwork and concrete pour from 10pm–6am. 


Earth works (ongoing)

Bulk earth works to the southern end of the platforms, installation of drainage and kerbing to future southern car park and bus interchange.

Pipe and electrical service installation, foundation and slab works, and building retaining walls.